A petrol station by the E17 slip road chose fast charging in 2021, and has grown with every generation of chargers since.
Esso
Deinze
Fast charging at Tradit Energie
A filling station by the E17 access ramp chose fast charging in 2021 and has grown with each generation of chargers ever since.
Opening
2021
First fast chargers
Expansion
2022
2 × Alpitronic HYC150
Expansion
2023
Alpitronic HYC300
Expansion
2025
Alpitronic HYC200
Tradit Energie’s Esso station is on the Gaversesteenweg in Deinze, close to the E17 access ramp. In April 2021, the first electric cars charged at the new fast chargers in the presence of mayor Jan Vermeulen and alderman Filip Vervaeke. The mayor described the location as ideal: drivers can have breakfast or lunch on site while charging. Powerland installed the chargers and manages the charging.
The story of that opening can be read in Made in Oost-Vlaanderen: Esso tankstation Deinze klaar voor een groene toekomst (5 April 2021).
The challenge
A filling station is not an empty car park. Paving was already in place, an existing high-voltage substation needed to be connected, and the chargers would need room to grow later. From September 2020 to March 2021, our own teams worked on trenches, conduits, cables, drainage, kerbs and concrete. The chargers were in place on 8 March 2021 and connected the following day.
What made the difference?
One partner for the entire project. The same team that dug the trenches pulled the cables, installed the chargers, lighting and payment terminals, and arranged the inspection. This leaves no gap between the groundworks and the charger, and no dispute over who did what.
Eric Dewitte of Tradit Energie said in the article that the high-voltage substation was built for the future, with capacity that would eventually allow up to ten cars to charge at the same time. That room for growth has been used. Two Alpitronic HYC150 chargers were added in 2022, a HYC300 in 2023 and a HYC200 in 2025. Each Alpitronic has two 400 A charging cables, drivers can pay by bank card, and charging runs through our My.Powerland management platform. At the end of 2025, the HYC200 was moved to a new concrete base at the location of the first fast charger.
Vandotec knows this site inside out: according to Eric Dewitte in the article, our teams originally built the station and later expanded it.
Work delivered
2021
- Groundworks, cabling and foundation works
- Connection to the high-voltage substation
- Efacec HV350 ultrafast charger and two 50 kW Efacec QC45 fast chargers
- Three bank card payment terminals
- Six LED lighting columns with concrete bases and stainless steel protective bollards
- Inspection and commissioning
2022
- Two Alpitronic HYC150 chargers (2 × 150 kW) with four 400 A cables and cable management
- Two MID meters and two bank card payment terminals
- Four My.Powerland subscriptions
- Power cables and groundworks for the new chargers
2023
- Alpitronic HYC300 with two MID meters and two 400 A cables
- Dynamic load balancing with Smartgrid One
- Inspection of the installation
2025
- Alpitronic HYC200 with two 400 A cables and cable management
- Two My.Powerland subscriptions
- Inspection and as-built dossier
- Relocation of the charger to a new concrete base
Will your customers soon be charging at your filling station, shop or business site? Plan a no-obligation conversation with our charging experts.