One parking area in Ypres, three phases: from two fast chargers to a charging hub that keeps growing.

Project · Ypres

Charging infrastructure at Sitra Group

Powerland developed the charging infrastructure in Sitra Group’s parking area in three phases, from the first fast chargers to a further expansion with AC chargers.

Customer
Sitra Group
Location
Ypres
Period
2022–2026
Installation
AC and DC charging infrastructure

Key figures and installation

3 phases
2022–2026
2 × 150 kW
Alpitronic HYC150
4 × 400 A
DC charging cables
10 × 22 kW
Etrel AC chargers added in 2026

Three phases of expansion

Sitra Group began charging vehicles in its Ypres parking area in 2022. Powerland built the infrastructure, expanded it in stages and manages the chargers through My.Powerland.

2022–2023 · The first charging points

Powerland carried out cable, ducting and foundation works, then installed two 150 kW Alpitronic HYC150 fast chargers. Each charger has two 400 A charging cables. Two 22 kW Etrel Inch Pro AC chargers were also installed.

The initial quotation covered two Efacec chargers rated at 60 and 120 kW; at the customer’s request, the project moved to the more powerful Alpitronic chargers. The installation was inspected and handed over with an as-built dossier and SAT certificate.

2024 · Smart power management

Powerland added a Smartgrid One controller. It distributes the available power across the charging points to help prevent the connection from being overloaded.

2026 · Ten additional AC chargers

The site gained ten 22 kW Etrel Inch Pro AC chargers, mounted on five dual posts. Powerland also installed a new distribution board, laid cables and added wheel stops at each charging bay. The board leaves room for future expansion.

What made the difference?

One partner at every stage

The same teams know the installation and built each expansion on what was already in place.

Smart distribution supports expansion

Power management helps add charging points without a corresponding increase in peak demand.

Management through My.Powerland

Powerland manages the chargers, charging sessions and billing through My.Powerland.

Will your business soon need more charging capacity than planned? Plan a no-obligation conversation with our charging experts.

Delivered by Powerland
  • DC fast charger
  • AC charging station

Contact and help

Our customer service and sales team are ready to assist you.
If you are at a charging point and require immediate assistance, you can reach us at +32 57 69 01 05 to speak to an employee.
For non-urgent questions regarding billing or your account, you can email info@powerland.be

Get in touch