Coach Partners shows how to phase a charging project intelligently: first the grid capacity and electrical infrastructure, then the chargers. The result is an installation ready to support electrifying the entire fleet.
Coach Partners Maldegem
Maldegem
Realisation · Maldegem
From medium-voltage substation to a 600 kW fast-charging station
In Maldegem, Powerland built charging infrastructure for Coach Partners’ electric buses and coaches, from the electrical foundation through to the chargers.
Client
Coach Partners – Van Hoorebeke en Zoon
Location
Maldegem
Sector
Passenger transport · buses and coaches
Solution
Medium-voltage substation, DC fast charging and AC charging
Key figures and charging setup
1,600 kVA
Medium-voltage substation
600 kW
Kempower fast-charging system
8
DC charging points
8 × 22 kW
ETREL AC charging points
Coach Partners in Maldegem
Coach Partners is one of the largest independent bus operators in Flanders. The group was formed through collaboration between several family businesses, including Van Hoorebeke en Zoon in Maldegem. Coach Partners renews its modern fleet every year; electrification is the next step.
Electric buses and coaches require substantial power. Coach Partners therefore wanted one partner to manage the full project, from medium voltage and low-voltage distribution to chargers, cabling and the charging platform.
A charging project delivered in two phases
Powerland first put the electrical foundation in place and included outgoing connections in the main switchboard for future chargers. The charging equipment and cabling followed in a second phase. This phased approach allowed the site to expand without duplicating work.
Phase 1: medium and low voltage
Powerland supplied and installed a new 1,600 kVA medium-voltage substation with an automatic recloser kit. The work also included the substation groundworks and rerouting the existing drainage pipe.
The new main low-voltage switchboard has heavy-duty outgoing connections for the fast-charging system, a separate supply for the existing building and connections for the AC charging points.
Phase 2: DC and AC charging
The Kempower C-Series fast-charging system consists of a central 600 kW power unit and six satellites: two with dual connectors and four with a single connector. Together, they provide eight DC charging points. Available power is dynamically distributed among the vehicles charging at that time. Cable retractors keep the charging cables tidy and safe.
For AC charging, Powerland installed four dual charge posts with 22 kW ETREL Inch Pro chargers, providing eight AC charging points. The posts are mounted on concrete plinths for vehicles that stay on site for longer.
Cabling, configuration and inspection
Powerland installed approximately 1.4 km of heavy-duty power cable between the substation and the power unit, along with data cables for communication. The associated groundworks were also completed. Powerland connected and configured all charging points on the charging platform, and prepared the full project file and inspection of the installation.
Ready to electrify your fleet?
Powerland supports you from the grid connection and medium-voltage substation through to a fully operational charging station for cars, buses and trucks.